HIDALGO COUNTY REGIONAL MOBILITY AUTHORITY

 

DYNAMIC PROJECT STATUS MEMORANDUM

 

Hidalgo Loop

&

Hidalgo Trade Corridor

 

 

 

LAST UPDATED 1/19/10

 

Table of Contents

GENERAL INFORMATION: 1

STATUS OF HIDALGO LOOP: 1

PUBLIC MEETINGS: 1

SCHEMATICS: 1

Preservation of ROW for technically preferred alignment (TPA): 1

Status of the loop on the Metropolitan Transportation Plan (MTP): 2

ENVIRONMENTAL DOCUMENT: 2

PHASE ONE - PLANNING STUDIES. 2

PHASE TWO – NEPA DOCUMENTATION.. 3

TRANSPORTATION REINVESTMENT ZONE (TRZ): 3

PENDING ITEMS: 3

PROPOSED ACTION: 3

HIDALGO LOOP TRAFFIC AND REVENUE (T&R) STUDIES. 4

HIDALGO LOOP FINANCING.. 5

STATUS OF PASS THROUGH APPLICATION.. 5

STATUS OF “HIDALGO TRADE CORRIDOR”. 5

SCHEMATICS. 5

PENDING ITEMS: 5

PROPOSED ACTIONS: 5

STATUS OF THE “HIDALGO TRADE CORRIDOR” ON (MTP) 6

ENVIRONMENTAL DOCUMENT.. 6

International Bridge Trade Corridor: 6

Connector Corridor: 6

PENDING ITEMS: 6

PROPOSED ACTIONS: 7

HIDALGO TRADE CORRIDOR TRAFFIC AND REVENUE (T&R) STUDIES  7

PENDING ITEMS: 7

PROPOSED ACTIONS: 7

HIDALGO TRADE CORRIDOR GMP REVIEW AND FINANCING.. 7

PENDING ITEMS: 7

PROPOSED ACTIONS: 7

 

ATTACHMENTS

Appendix A - Hidalgo Loop Map

Appendix B - Hidalgo Trade Corridor Map

Appendix C - Hidalgo Loop Resolutions of Support From all Entities

Appendix D - Status of Coordination for Preservation of Right of Way For Hidalgo Loop

Appendix E – Status of Hidalgo Loop and Hidalgo Trade Corridor on MTP

Appendix F - HCMPO Thoroughfare Plan Map

Appendix G - Transportation Reinvestment Zone #1 Resolution by HCCC & Interlocal Agreement with HCRMA

Appendix H - Transportation Reinvestment Zone #1 Map

Appendix I - TxDOT Opinion Regarding TRZ Requirements  

Appendix J – C&M Level II T&R Summary Results and Revised Scope of Services for FSW

Appendix K - Hidalgo Loop Pass Through Application Letter

Appendix L - Request from HCMPO to Place “Hidalgo Trade Corridor” on MTP

Appendix M - TxDOT Letter of Support and “TIGER” Grant Application for International Bridge Trade Corridor

Appendix N - TxDOT Letter of Support and “TIGER” Grant Application for the “Connector Corridor”

Appendix O – Executive Director Contract (Mr. Godfrey Garza)

Appendix P – RMA Adopted Environmental Rules


-Dynamic Project Status Memorandum-

Hidalgo Loop and Hidalgo Trade Corridor

           

GENERAL INFORMATION:

 

“Hidalgo Loop” has reached a critical stage of the Project Development Phase.  The reason it is at a critical stage is that the Hidalgo Toll Loop Project Development is reaching a milestone meaning that certain phases will have reached a logical point for stoppage due to shortage of funding to finance the entire loop. 

 

This financial shortage has mandated that HCRMA to concentrate its efforts on constructing the “Hidalgo Trade Corridor”.  This Corridor would allow connectivity from several International Bridges to US 83 Expressway via tolled controlled access facility.  Based on a Preliminary financial plan, it is predicted that this Corridor will have a much better potential to be fully financed than the original “Hidalgo Loop”.

 

The HCRMA has advertised, interviewed, selected, and negotiated an Executive Director position with Mr. Godfrey Garza effective 11-12-2009. Mr. Garza will provide the authority with administrative and managerial services, including project development services. Mr. Garza will also provide the Authority with a monthly report of activities and efforts made in furtherance of the project development. Such report shall be provided at regularly scheduled public meetings of the Board of Directors of the Authority.

 

The intent of this website is to provide updates on the status of both “Hidalgo Loop” and “Hidalgo Trade Corridor”.

 

STATUS OF HIDALGO LOOP:

 

PUBLIC MEETINGS: 

Over 20 successful Public Meetings were held on Sections A, B, C, D, E, & F.  Results of all Public Meetings regarding comments received have been summarized and documented (see additional details under the Environmental document Section).  Resolutions have also been received from all effected cities supporting the proposed alignments (attached).

 

SCHEMATICS: 

Schematics for Sections A, B, C, & D have been completed and submitted to TxDOT.  Schematics for Sections E & F are being reviewed and will be submitted to TxDOT by November 2009.

 

Preservation of ROW for technically preferred alignment (TPA):

Even though the entire loop cannot be financed for construction at this point in time & since (TPA) is already identified and has gone through successful Public involvement, HCRB is actively working with all cities, the county, and MPO in order to obtain concurrence from the entities to protect the needed ROW of the Loop for (TPA) from development (see attached status of coordination).  Preservation of this corridor is essential for future development of the project, by making the loop more financially feasible in future.  Hidalgo Loop (TPA) will remain on the MPO thoroughfare plan (see attached map).  Requests will also be made for placement on County and City thoroughfare plans.

 

Status of the loop on the Metropolitan Transportation Plan (MTP):

Hidalgo County Metropolitan Planning Organization (MPO) has a 25 year financially constraint list of projects referred to as MTP.  HCMPO is currently working on the MTP Plan Update, which will cover the next 25 years from 2010 to 2035 and is required to be completed by December 2009.  The MTP is a comprehensive blueprint for transportation systems and services aimed at meeting the mobility needs of the area.  Since the entire loop is not financially feasible as this point in time, a request has been made by the HCRMA to the HCMPO to remove the entire loop from this document.  A new project referred to as “Hidalgo Trade Corridor”, explained in detail later on this website, which is financially feasible has be placed on the MTP in preliminary form and awaiting approval.   

 

 ENVIRONMENTAL DOCUMENT:

 

Environmental assessment document preparation were well underway for Section A and partially underway for Section C, however, a determination by Federal Highway Administration (FHWA) that these sections (A&C) need to go through a much more detailed process of Environmental impact statement “EIS” brought a “halt” to the entire process and no further activity is proposed on the Hidalgo Loop at this time.  The following activities have been completed in incompliance with National Environmental Policy ACT (NEPA) requirements.  It is important to note that most of the data collected will be used to complete the NEPA requirements of the “Hidalgo Trade Corridor” discussed later in further details.

 

PHASE ONE - PLANNING STUDIES

 

MPO Coordination/Need and Purpose

·         Need and Purpose defined and reviewed with MPO.

·         Coordinated with MPO regarding project status in MTP.

·         Need and Purpose Chapter prepared for Sections A, B, C, and D.

 

Constraints Mapping/Analysis Matrix/Preliminary Alternatives Development Report

·         Constraints mapping and analyses prepared for four series of public meetings (May 2008, August 2008, February 2009, and June 2009).

·         Preliminary Alternatives Development Report drafted for all sections.

·         Alternatives chapter prepared for Sections A and C.

 

Draft Environmental Classification Letters

·         Submitted Sections A and C Environmental Classification letters in January 2009.

·   Environmental Classification letters drafted for Sections B and D but not submitted.

 

 

Public Meeting Summary Reports

·         Prepared and submitted for May and August 2008 public meetings (Sections A, B, C, and D).

·         Reports for February and June 2009 being finalized (Sections B, D, E, and F).

 

PHASE TWO – NEPA DOCUMENTATION

 

Environmental Document Preparation

·         Conducted field surveys for all parcels for which right of entry was granted for Sections A and C.

·         Preliminary Draft EA prepared for Section A.

·         Wetlands Report and Historic Resources reports drafted for Section A.

 

TRANSPORTATION REINVESTMENT ZONE (TRZ):

 

On December 16, 2008, Hidalgo County Commissioner Court authorized the establishment of TRZ #1 through issuance of an order (see attached).  The order indicated:

“The Hidalgo County Commissioners Court will take action in the future to establish an economic development fund and facilitate the collection and use of a designated portion of the abated taxes for the benefit of the Hidalgo Loop Project.”  It also indicated:

“The portion of the tax increment on property within the zone that will be abated and dedicated for use directly for the Hidalgo Loop Project, and the means to collect those amounts for such use, will be established through action by the Commissioners Court and interlocal agreement with HCRMA.”

 

PENDING ITEMS: 

(An interlocal agreement between Hidalgo County and HCRMA needs to be executed to clarify items 1 & 2)

 

1.      The distribution of taxes collected will be 50% Hidalgo County & 50% HCRMA.

2.      Establish a procedure to facilitate the collection and use of a designated portion of the abated taxes.

3.      Current TRZ Boundaries (TRZ #1) as approved by the county needs to be revised.  If revision to the Boundary is not allowed by law, then a new TRZ needs to be created.

The reason for this revision is that through Public involvement, changes were made to alignment “D” in the vicinity of US 83 Expressway and US 281 Expressway connections that are not shown in the current TRZ Map.

4.      A new TRZ needs to be created for alignments E and F.

 

PROPOSED ACTION: 

 

1.      An Interlocal Agreement has been prepared between HCRMA and Hidalgo County to formalize the 50-50 distribution of collected taxes.  This agreement was approved by the HCRMA Board as well as to Hidalgo County Commission Court.

2.      Action on the procedure to facilitate the collection of abated taxed is being delayed.  The reason for the delay is the following:

 

SB1266, relating to pass-through financing and the designation and operation of Transportation reinvestment zones, section 3(i) indicate the following:

“To assist the county in developing a project authorized under section       222.104 (Pass-through), if authorized by the commission (TxDOT Commission) under Chapter 441, a road utility district may be formed under that chapter that has the same boundaries as a transportation reinvestment zone created under this section.”

 

Transportation code, Chapter 441.030 states:

Confirmation Election

a) Not later than the 15th day after the date that all temporary directors (of the road utility district) shall meet and order an election in the boundaries of the proposed district to confirm the creation of the district and elect the directors of the district.

 

Transportation code Chapter 441.035 states:

        Including Bond Proposition at Election

a)  At the election, the temporary directors may include a separate ballot proposition to approve the issuance by the district of bonds payable from ad valorem taxes.

 

TxDOT Opinion regarding the creation of a ROAD UTILITY DISTRICT:

TxDOT through a memorandum titled Transportation Reinvestment Zones dated March 18, 2008 indicated as following:

 

     Question: Does the creation of a Road Utility District require an election?

     Answer: Yes, Texas Transportation Code 441.030 and 441.035 require a confirmation election and bond election if the Road Utility District will be issuing bonds payable from ad valorem taxes.

 

Due to these current requirements of having to create road utility district and elections requirements and the possibility of another bill during the next legislative session to eliminate these requirements, the action is being delayed.

 

3.            None are proposed at this time.

4.            None are proposed at this time.

 

HIDALGO LOOP TRAFFIC AND REVENUE (T&R) STUDIES

 

-    C&M Consulting firm to date has performed 3 Level II T&R studies on the Hidalgo Loop to determine the toll feasibility and projected revenue for the loop.  The summary results of T&R for the following sections are attached to this report.

1.            Section A&B

2.            Section A only

3.            Section B & Section A (only to Anzalduas Crossing)

 

 

 

 

 

HIDALGO LOOP FINANCING

 

-    The original “Preliminary Project Development Agreement” (PPDA) executed between HCRB and the HCRMA required that HCRB to provide a “guaranteed max price” (GMP) for project delivery as well as a “Risk Based Financial Plan” (RBFP).

-    HCRB did submit a Preliminary GMP, However, due to downturn of global economy and its effects on financial markets was not able to provide a RBFP for any portion of the loop.

-    PPDA has now been amended to require that HCRB will only provide a GMP for the limits of “Hidalgo Trade Corridor” and the Proposed Financing of that GMP will be provided by 1st Southwest group who act in the capacity of financial advisors to the HCRMA.  Please see further details under the Hidalgo Trade Corridor Section.

 

STATUS OF PASS THROUGH APPLICATION

 

On May 12, 2009, HCRMA formally submitted a pass-through finance application to TxDOT for Section “A” and Section “B” of the Hidalgo Loop (see attached letter).  HCRMA elected to use revenue from 3 local sources to combine with $377,802,000 of pass through payments requested from TxDOT to fund Sections “A” and Section “B”.  These local sources include toll revenue, tax increment revenue from Hidalgo County Transportation Reinvestment Zone (TRZ) No. 1 and revenue from a surcharge on vehicle registration fee in the county.  TxDOT Commission did not authorize any negotiations to begin on this application. 

 

STATUS OF “HIDALGO TRADE CORRIDOR”

 

As was mentioned before, due to available financial resources, HCRMA is now pursuing development of this new project, which allows connectivity from several international bridges to US 83 Expressway.  Hidalgo Trade Corridor consists of 2 completely separate projects.

 

SCHEMATICS

 

PENDING ITEMS:

1.            The connection of “Connector Corridor” to FM 1016 needs to be revised from the original schematic.  L&G Engineering Consultants will investigate the advantages and disadvantages of an at grade crossing at FM 1016 vs. an Overpass at FM 1016.

2.            The connection of “International Bridge Trade Corridor” from FM 3072 to SP600 needs to be added to the original “B” Schematic.  The reason for this change is that limits of this corridor under the Hidalgo Loop project has been changed.

3.            L&G Engineering Consultants will investigate the advantages and disadvantages of providing a director connector to US 83 Expressway vs. an Overpass (Trade Corridor over US 83 Expressway).

 

PROPOSED ACTIONS:

1.            L&G Engineering has successfully completed this task and turned in the work product to both TxDOT and the HCRMA.

2.            L&G Engineering has successfully completed this task and turned in the work product to both TxDOT and the HCRMA.

3.            This task has been vetted with the HCRMA Planning Committee and the decision to construct an Overpass at US83 in lieu of a Direct Connector. This exhibit has been provided to both TxDOT and HCRMA.

 

STATUS OF THE “HIDALGO TRADE CORRIDOR” ON (MTP)

 

Hidalgo County Metropolitan Planning organization (MPO) has a 25 year financially constraint list of Projects referred to as MTP.  Since the Hidalgo Trade Corridor is financially constrained, a request has been made by HCRMA to place it on the MTP (see attached request along with Financial Plan). At this point, the MTP is still not finalized until it is adopted by the MPO Policy Board but as identified on this Map, the HTC has been placed on it.

 

ENVIRONMENTAL DOCUMENT

 

International Bridge Trade Corridor:

This corridor connects both Pharr International Bridge as well as Donna International Bridge to US 83 Expressway Corridor.  This corridor will be locally funded (No Federal, No State Dollars) and HCRMA plans to comply with the Environmental rules adopted by the HCRMA (see attached) which will not require TxDOT or FHWA approval.  “TIGER” grant funds (Federal Stimulus Funds) have been requested for the connection of this locally Funded Project to US 83 Expressway by means of a proposed direct connector (see attached letter of support from TxDOT).  If the “TIGER” Grant Funds are awarded, then HCRMA Plans to follow provisions provided in the Texas Administrative Code (TAC) to perform an Environmental Assessment Document for this connection.  This will require approval of TxDOT and possibly FHWA.

 

Connector Corridor:

This corridor will connect the International Bridge Trade Corridor to the existing FM 1016 facility.  Construction of this corridor will allow connectivity of 2 additional International Bridges namely Anzalduas International Bridge as well as Hidalgo-Reynosa International Bridge to US 83 Expressway.  This corridor will utilize local funds as well as Federal and State Funds.  Preliminary discussions with FHWA have indicated that since this corridor will only connect an existing facility (FM 1016) to an existing locally Funded Project (International Bridge Trade Corridor), it can be developed by an Environmental Assessment (EA) Process, rather than an Environmental Impact Statement (EIS).

 

“TIGER” Grant funds (Federal Stimulus Funds) has been requested for a bridge connector over the Anzalduas International Bridge. (see attached letter of support from TxDOT) If the TIGER grant funds are awarded, provisions provided in the TAC will not be required, since the project will already be following the “EA” process.

 

PENDING ITEMS:

1.            Negotiate a fee schedule with PBS&J to complete an EA on Hidalgo Trade Corridor Projects.

2.            Submit a classification letter to FHWA to formalize their decision on an EA document for the connector corridor.

3.            Submit a classification letter to TxDOT (and possibly to FHWA) to formalize this decision on an EA document for the International Bridge Trade Corridor following TAC provision if TIGER grant funds are awarded.

 

PROPOSED ACTIONS:

1.            PBS&J fee to complete the EA for Both Projects were approved by the HCRMA on 9-16-09.  PBS&J will be a sub-contractor to Blakely Fernandez (HCRMA Attorney).

2.            EA document preparation is complete on the “International Bridge Trade Corridor” and is anticipated to be delivered to the HCRMA Board meeting in February, and a classification letter to FHWA on the connector project will follow at a later date.

3.            No action is required unless “TIGER” grant funds are awarded.

 

HIDALGO TRADE CORRIDOR TRAFFIC AND REVENUE (T&R) STUDIES

 

PENDING ITEMS:

1.            C&M Consulting firm to perform a level II T&R studies on this corridor and include the impact of Mexican trucks on T&R.

 

PROPOSED ACTIONS:

1.            C&M is currently performing this task as a subcontract to 1st Southwest Group. (See attached scope)

 

HIDALGO TRADE CORRIDOR GMP REVIEW AND FINANCING

 

As was mentioned before, HCRB will only provide a GMP for this corridor and the Proposed financing of that GMP will be provided by the First Southwest Group, who act in the capacity of financial advisors to the HCRMA.  GMP, which was submitted by the HCRB and subject to negotiations and final approval by the HCRMA, will provide a “fixed financial target” that will be required to complete this corridor.  Completion of this corridor will include preparation of construction plans, acquisition of the needed Right of Way, adjustment of Utilities, Environmental Mitigation, Advertising and Award of Construction Contract, Construction Inspection and Material Testing, as well as change orders during construction.  HCRMA, through its consultant PBS&J will provide the environmental clearance for the project.

 

PENDING ITEMS:

1.      HCRB to submit the “GMP” by October 16, 2009

2.      HCRMA to negotiate the terms of the “GMP” with HCRB

3.      After negotiations are complete, First South West (FSW) needs to determine how the “GMP” can be financed

4.      If the “GMP” can be financed, execute a final “Project Development Agreement” (PDA) with HCRB

 

PROPOSED ACTIONS:

1.      HCRB submitted the GMP on October 16, 2009

2.      At the 11-17-09 HCRMA Board Meeting, action was taken to approve the hiring of 2 “Engineering Consultant” firms (S&B Infrastructure, LTD. and Raba-Kistner Infrastructure) to position itself for negotiations of the “GMP” terms

3.      FSW has received from C&M a revised T&R that included revenue generated from Mexican Truck Traffic. (revised T&R due 12-10-09) C&M has been authorized to do an “Investment Grade Study” to further along the financing package.

4.      No action taken at this time

 

ATTACHMENTS

 

Appendix A - Hidalgo Loop Map

Appendix B - Hidalgo Trade Corridor Map

Appendix C - Hidalgo Loop Resolutions of Support From all Entities

Appendix D - Status of Coordination for Preservation of Right of Way For Hidalgo Loop

Appendix E – Status of Hidalgo Loop and Hidalgo Trade Corridor on MTP

Appendix F - HCMPO Thoroughfare Plan Map

Appendix G - Transportation Reinvestment Zone #1 Resolution by HCCC & Interlocal Agreement with HCRMA

Appendix H - Transportation Reinvestment Zone #1 Map

Appendix I - TxDOT Opinion Regarding TRZ Requirements  

Appendix J – C&M Level II T&R Summary Results and Revised Scope of Services for FSW

Appendix K - Hidalgo Loop Pass Through Application Letter

Appendix L - Request from HCMPO to Place “Hidalgo Trade Corridor” on MTP

Appendix M - TxDOT Letter of Support and “TIGER” Grant Application for International Bridge Trade Corridor

Appendix N - TxDOT Letter of Support and “TIGER”Grant Application for the “Connector Corridor”

Appendix O – Executive Director Contract (Mr. Godfrey Garza)

Appendix P – RMA Adopted Environmental Rules